Safety Standardization of ×× Project
Reporting Materials
The construction site of ×× Project is located at the northeast corner of the intersection of Weisan Road and Jingliu Road in Zhengzhou City. There is one underground floor and twenty-three floors above ground. The building height is 75.35 meters. It is a first-class building with a shear wall structure. The construction unit is XX Co., Ltd.; the design unit is XX Design Institute; the supervision unit is XX Company. The project investment is 30 million yuan. The construction start date is March 1, 2006, and the planned completion date is June 1, 2007. The main structure of the project currently has three floors.
Since the start of the project, it has received great attention, help and care from the Zhengzhou Key Construction Project Quality Supervision Station, Party A and the supervision department, as well as our company. Management objectives for safe and standardized construction sites were determined. Leaders from all parties have come to the construction site many times to inspect, deploy and guide the work, and have given the project department great support and help in terms of human, material and financial resources. The project department is determined to work hard to improve the level of safety and civilization management, repay the support and help of leaders at all levels with practical actions, organize carefully, strive to create a safe and civilized construction site, and ensure safe construction and improve economic benefits while ensuring project quality and progress. , establish the style of XX company, and strive to shape this project into a high-quality project in the Henan construction industry.
Through the efforts of all project department personnel and the care and support of leaders at all levels, the project has not had a single casualty accident since the start of construction, maintaining the expected goal of "zero accidents" and on-site safety management is high Starting point, high standards, strict and standardized management.
During the construction of the project, the project department strictly implemented the safety management construction requirements for all work, each process, each construction team and team, and called on the employees to carry forward the spirit of ownership, boldly innovate, and constantly explore, Continuously summarize and improve. Now the project department’s work in safety and civilized management is reported as follows:
1. Attach great importance to the ideological aspect:
1. The project department keeps in mind that “today’s site is tomorrow’s "market", establish and improve the "safe and civilized construction" management organization, and establish a safety leadership group led by the project manager, a safety inspection team composed of deputy project managers, full-time safety officers, equipment managers, materials personnel and construction foremen. , full-time safety officers conduct uninterrupted inspections every day, the team conducts safety construction inspections once a week, and conducts a safety assurance system once a month. The leadership, supervisory level, and operating levels have clear responsibilities. Those who have made outstanding contributions to safety and civilized management will be commended and given material rewards; illegal operations will be criticized and educated, and financial penalties will be imposed in serious cases. Fully mobilize the enthusiasm of employees.
2. Adopt a method that combines education and management. New workers who enter the site should be educated first and then put on the job. In particular, special operations personnel should be trained first and then put on the job. While carrying out safety education when entering the site, education will be carried out regularly and irregularly during the construction process to effectively implement the policy of “safety first, prevention first”.
3. In accordance with the "three norms and one standard" combined with the characteristics of this project, prepare a construction organization design, improve various rules and regulations, and ensure that safety work is "planned before construction and controlled during construction" ", there will be a summary after construction" to implement responsibilities.
2. Set goals and strengthen safety management
The safety construction goals set by our project department for this project are: Strictly implement the "Building Construction Safety Standard" JGJ59-99 and the company's "Occupational Health Safety Management System" GB/T28001-2001 regulations ensure that the entire construction process achieves the following safety objectives:
1. Prevent fire accidents in this project;
2. Prevent fire accidents in this project Major casualty accidents;
3. This project will prevent equipment accidents;
4. This project will prevent the occurrence of occupational diseases;
5. This project will cause minor injuries The accident frequency is controlled below 1.5‰;
6. The construction site ensures a "provincial-level safe and civilized construction site" and strives to create the "Zhongzhou Uneasy Cup".
To this end, the project department has taken the following steps:
⑴ Strengthen the standardized management of safety. The project department has formulated the "Safety Work Plan", "Labor Protection Measures Plan", "Occupational Health and Safety" around this goal Management Plan and Construction Organization Design", etc., improved systems and measures, and established a systematic safety assurance system. The job responsibility system has been clarified. The project department has signed a letter of responsibility with each manager, and has established various rules and regulations. It conducts major inspections on quality, safety and civilized construction, rewards and punishes according to the rules and regulations, and corrects existing problems in a timely manner.
⑵. Carry out safety education in a timely manner. According to the safety and civilization education system, the project department conducts safety and civilization education for each batch of laborers entering the site, and establishes safety education files for each laborer so that they can establish a basic Safety awareness, and record daily safety and civilized activities in the safety production diary. Regularly organize study classes to organize managers to learn safety regulations, safety knowledge and important speeches on safety by national leaders to improve safety management levels.
⑶. Focus on key points, find key points, and carry out key prevention. The construction site is complex and changeable. The project department determines the key prevention contents of this project based on the specific conditions of the project. The project department formulates strict measures and organizes them in a timely manner. Implementation: First, safety technical education and briefings are carried out step by step, and safety precautions and personal protective equipment are implemented. Special operators must pass the training and examination and then hold a certificate to work. After installation or construction is completed, they must be inspected and accepted and the acceptance procedures can be completed before they can be put into use. , and hang safety signs in accordance with regulations.
⑷. Targeted control of key points and difficulties in construction. Before the construction begins, a special construction plan will be prepared and submitted for review and approval before implementation. Including temporary power construction organization design, external scaffolding construction plan, unloading platform erection plan, safe construction organization design and other special plans, and submit them to the supervision department and the company's engineering department for approval as required, and then organize implementation, inspection, rectification, and continuous Improve safety management levels.
Develop various safety technical assurance measures and organize their implementation:
A. Conduct three-level safety education for all entry personnel, and provide safety measures for construction operators who fall from heights, are struck by objects, Conduct safety awareness training on machine tool injuries, electric shock injuries, etc.
B. When issuing construction technical briefings for each sub-item, safety precautions must be included. Before work, the operation team should conduct a safety production briefing as a team unit and archive it.
C. Establish a self-protection awareness of three no harms (I do not harm myself, I do not harm others, and I am harmed by others) during the construction process. Full-time safety officers provide education and supervision at any time.
D. Protect the four entrances and five edges. The safety protection facilities must meet the safety requirements. Protective measures should be taken at stairwells, elevator entrances, passageways, reserved openings and edges.
E. During the construction of the project, rope nets will be used for horizontal protection, and dense mesh safety nets will be used to seal the facade of the project. The safety net used must be tied firmly with lead wire. The safety officer, together with the construction workers and technicians, will jointly inspect and accept the product and sign for confirmation before it can be put into use.
F. All equipment (except tower cranes) should be equipped with fixed or movable protective sheds. The primary and secondary power supply connectors should have protective devices. The machinery should be used in strict accordance with the operating procedures. Illegal operations are strictly prohibited. Operators must be qualified after professional training.
G. All on-site distribution boxes should use standard metal distribution boxes or power distribution boxes with hazard signs and dedicated management. The circuits should adopt a three-phase five-wire system, and each and secondary wiring must be Sensitive and effective leakage protectors should be installed. Professional electricians are responsible for daily inspection, maintenance and protection work.
H. Tower cranes strictly implement the safety application and acceptance approval system. The ultra-high amplitude limiter and torque limiter are sensitive and reliable, and the safety devices of the hook and hoist are reliable. Insulating boards should be laid in the driver's room. Operators should hold certificates to work. It is strictly prohibited to work due to human-machine fatigue. It is strictly prohibited to work in migrant workers' houses and under overweight conditions. Rotate over the danger zone.
I. Set up fire pools, fire buckets and other fire fighting equipment on site, and designate dedicated personnel to manage them.
J. Ensure the effective operation of the safety management system and management system, implement heavy rewards for safe construction, and impose heavy penalties for illegal operations.
K. Design a safety protection plan. After the project starts, promptly carry out safety protection on the construction working surface, construction passages and places where people move. This project adopts a cross-coordinated protection system on both horizontal and vertical sides. Protection includes safe passages, safety protection sheds, overhanging flat net protection, hole protection, work surface protection, etc. Facade protection includes: vertical net protection, edge protection, etc.
⑸. Increase investment and take precautions before they happen. In order to ensure the safe and civilized construction of this project, in line with the principle of "safety first, prevention first", the project department invested a lot of financial and material resources to strengthen safety protection facilities and prevent the occurrence of safety accidents. In terms of temporary power consumption, the "TN-S" zero-connection protection system is adopted, and "three-level power distribution, two-level protection" is implemented. More than 300 meters of various cables have been replaced, and five-core cables that meet the new standards have been replaced. Purchase 20 standard distribution boxes and 65 leakage protectors, so that one machine has one gate and one leakage box. The distribution boxes are locked, painted and numbered, and the equipment name, circuit diagram and control system are clearly marked: In terms of fire protection, 36 dry powder fire extinguishers, 24 fire buckets, and 420 meters of various water pipes were installed; in terms of preventing high-altitude falls, 8,000 square meters of dense mesh safety nets, 300 square meters of safety nets, and 1,500 square meters of protective sheds were installed. The standard protective railings on the side are 1,600 square meters, and the elevator opening adopts a standard square frame dense mesh steel mesh protective door. A method of combining plane protection and vertical net protection has been established, which has achieved good results. Safety slogans and safety warning signs have been hung. The vertical main scaffolding adopts cantilever scaffolding, and a special plan has been compiled. In terms of protective equipment, more than 200 safety helmets, 80 safety belts, 240 pairs of non-slip shoes, more than 150 pairs of insulating gloves and 240 pairs of rubber boots were purchased.
"Three treasures, four mouths and five borders" protection work. Safety helmets are worn by different personnel in different colors according to regulations, and the colors must be harmonious. Safety belts must be fastened according to regulations when working at heights. The "four entrances" are all protected by railings, painted with yellow and black paint, the reserved holes are protected by covers, and the edge protection is jointed by steel pipes and steel bars, which is simple and cost-effective.
3. Pay attention to civilized construction and create a beautiful environment
Civilized construction is an important indicator that reflects the management level of the project department and is a concrete manifestation of the company's image. During the specific implementation process, the project department strictly followed the company's on-site civilized construction standards for layout, ensuring that the walls were beautiful, the gates, and slogans were eye-catching and neat, and the construction roads were clean and hygienic. To this end, a detailed civilized construction plan was formulated.
1. In terms of site planning, the project department made an overall layout and unified planning for the site. Standardized walls and gates were built around the site. Closed management was implemented on site. Above the gates and door heads, the company required The company logo and promotional slogans were painted, and a large banner was hung in a prominent position at the gate.
2. In terms of temporary construction facilities, the working area is separated from the living area. The hardened concrete road is more than 300 meters long, the standardized migrant workers’ dormitories are more than 2,400 square meters, the staff dormitories are more than 1,200 square meters, and the renovated offices are more than 1,500 square meters. , a hardened sand and stone quarry of more than 900 square meters, and a standardized cement warehouse, staff canteen, toilets, showers and other temporary facilities have been built. The migrant workers' dormitories are kept clean, the canteen uses gas appliances, and measures are taken to prevent rats and flies. A swill bucket is set up at the door and is cleaned every day. The toilets are cleaned by designated personnel and flies are regularly disinfected.
3. In terms of personnel appearance, the project invested funds to customize work clothes for employees in accordance with the company's requirements, and implemented uniform dress and badges. Establish a good corporate image and enhance the collective sense of honor and pride of all employees.
4. In terms of construction site management, the working surface is required to be clean of materials after work, and garbage is not allowed to be left on the working surface overnight. Each working surface is inspected every afternoon before get off work, and those found not to meet the requirements will be punished. . Make sure the construction site is clean. On both sides of the main road in the site, the project department arranged potted seasonal flowers to create an elegant and fresh environment for the site.
The main sources of noise pollution, such as the woodworking workshop, were fully enclosed and a sewage sedimentation tank was installed.
5. Material storage is an important part of civilized construction. Due to the narrow site, the project department divided the storage areas for various finished products, semi-finished products and turnover materials according to the general layout of the construction plane. Items are required to be stacked in square piles, horizontally and vertically, and classified and hung with signage.
Since the start of the ×× project, it has received strong support and help from the quality supervision department, Party A and the supervision department, as well as the company and brother units. The project output has been along the lines of "high starting point, high level, high level" We strive to achieve the goal of "quality, high efficiency, and high efficiency". We realize that although safety management has achieved certain results now, safety management should be consistent and must not be relaxed. We are determined to continue our efforts in future work, strictly manage, strive for excellence, and create Advanced project department, create a better safe and civilized construction environment, and create more and greater social and economic benefits for XX Company.
×× Engineering Co., Ltd.
×× Project Department
X, month, x, 2011