Do you want to lay wall tiles or floor tiles first?

Many owners have a question when laying tiles in the kitchen and bathroom. Which is the first to put up the wall tiles? Or do you want to lay the floor tiles first? These two spaces are the most frequently used in life, followed by the frequency of water use. If the shop is not handled properly, it will bring a lot of trouble to the later residence. Today, Bian Xiao will bring you the advantages and disadvantages of these two paving sequences. Let's have a look.

1. Stick the wall tiles first, then the floor tiles.

The newly paved floor tiles need to stand for two to three days before pressing, otherwise the flatness of the ground will be affected. Therefore, in order not to affect the construction progress, workers often lay wall tiles first and then floor tiles, so they always retreat to the door. After it is completely paved, no one is allowed to enter, so that it has a certain time to solidify and dry.

But there are also disadvantages: if the wall tiles are laid first, and then the joint size of the floor tiles is reserved, it is difficult to reserve the appropriate size. There is too little left to lay floor tiles; There is too much left, and the gap between the wall and the ground is too big.

If the gap between the wall and the ground is too large, the water on the wall will inevitably penetrate into the cement layer along the gap between the wall and the ground. After a long time, it is easy to produce odor or mold in the corner.

2. Lay the floor tiles first, then the wall tiles.

After the brick is built, the height of the ground is fixed. Workers can calculate the size of wall tiles from top to bottom in advance. In case there is a gap between the two, it can also be made up by cutting bricks.

Pave the floor first and then the wall. The gap between the two bricks is smaller and more beautiful. When water flows down the wall, it will flow directly to the floor tiles instead of infiltrating into the cracks of the tiles, and the ground water will not easily affect the cement mortar under the floor tiles.

But the disadvantage of doing so is that it is easy to damage the ground when other projects are carried out later. The newly laid floor tiles need to be cured for 2-3 days before pressing. So the ground is done first, and other projects are suspended.

summary

On the whole, the key to the entanglement of the two laying methods lies in their respective advantages and disadvantages.

Pave the wall first: there may be a problem that the reserved space is not suitable, leaving an ugly gap that cannot be repaired, resulting in a moldy smell in the corner.

Pave the ground first: the later project may destroy the paved ground and affect the project progress.

The above is about "laying wall tiles or floor tiles first?" The advantages and disadvantages of two laying sequences are introduced.