When will the relocation and resettlement house of Xinyang Dragon Bridge in Tinghu, Yancheng be completed?
According to the relevant information, it is expected to be completed and delivered in September next year. The relevant person in charge of the project said: the project officially started construction in April this year and is expected to be completed and delivered in September next year. At present, the main building engineering piles have been completed, and the basement piles have been completed by 60%. Support piles and dewatering tube wells are under construction.