How to write the completion acceptance information? Introduction to detail writing method

Completion acceptance data is the data formed in the project completion acceptance activities, including project acceptance summary, completion acceptance records, financial documents, audio-visual, microform and electronic documents, etc. How to write the completion acceptance information? The following will be introduced in detail!

I. Overview of the Project

1, general situation

Project name, building purpose, building location, construction unit, supervision unit, design unit, construction unit, building area, structure type, building number, etc.

2. Structural points

Foundation and foundation, columns, internal and external walls, beams, plates, internal and external wall decoration, ground decoration, roof structure, fire prevention equipment, etc.

3, mechanical and electrical system name

Name of electromechanical system included in the project.

4. Others

Refers to the content that needs to be explained in particular.

Second, the project completion summary

1, management

According to the characteristics and difficulties of the project, the project quality, site, contract, cost and comprehensive control are summarized.

2. Technical aspects

The summary of engineering technology should include the summary of new technologies, new products, new processes and new materials adopted in the project.

3. Experience

Summarize various experiences and lessons in the process of project implementation.

Three, the unit (child) project quality completion acceptance record

1, acceptance content

1. "Item", check the item by item.

The second is "quality control data verification".

The third is "safety and main use function verification and spot check results".

The fourth is "perceived quality acceptance".

The fifth is "comprehensive acceptance conclusion".

2. Signature of the acceptance unit

When the survey unit, design unit, construction unit, supervision unit and construction unit all agree to the acceptance, the project leaders of each unit shall personally sign and affix the official seal of the unit, indicating the year, month and day of signing and acceptance.

Four, the housing construction quality inspection report

1, compilation basis

Relevant laws, regulations and standards; Survey and design documents; The blue prints.the design, design change documents, etc.

2. Writing points

Foundation, main structure and function:

(1) survey and design changes (number of copies, reasons, whether it has been approved by the drawing review authority, etc.). );

(2) the realization of design intent (construction projects, parts and hidden dangers that are not changed according to design intent or design);

(3) the project acceptance opinions.

Handling of quality accidents:

Number of accidents, date of occurrence, implementation of treatment plan, etc.

Other aspects:

The above contents are not included, but they need to be put forward in the report.

Five, housing construction engineering quality evaluation report

1, compilation basis

Relevant laws, regulations, technical standards and engineering contracts.

2. Writing points

Foundation, main structure and function.

(1) Whether the construction meets the design requirements;

(2) Whether the raw materials, components and equipment meet the specified requirements;

(3) Whether the specified test and inspection items are all completed and effective;

(4) Whether all concealed works meet the specified requirements;

(5) Whether the divisional works, subdivisional works and inspection lot works have been accepted;

(6) rectification of problems raised by construction administrative departments, quality supervision institutions and supervision units;

(7) whether there are still controversial issues;

(8) Whether the construction progress meets the requirements and whether the construction period is reasonable;

(9) Whether there is illegal subcontracting and subcontracting.

3, unit engineering quality acceptance

(1) Whether the unit project quality has been accepted;

(2) Whether the contents stipulated in the project contract have been completed.

4. Handling of quality accidents

(1) Number of accidents, occurrence date and implementation of treatment plan;

(2) Whether there are still controversial issues and hidden dangers in accident handling.

5. Other aspects

Refers to the contents that are not included in the above contents but need to be put forward in the report.