1: Before pouring the road on the construction site, it is necessary to plan the position of the washing table, install the foundation beam template according to the size given in the installation instructions when pouring the road by the manufacturer, and pour the foundation beam. Generally, it is set at the right-hand side of the entrance to the construction site 10 meter.
2. Then, on the side of the washing platform far away from the road, dig a foundation pit of 2mX6m deep sedimentation tank and pour a concrete cushion with a thickness of 5- 10cm.
3. The wall of the sedimentation tank can be built the next day, and the specification requires three-stage sedimentation. That is, build a circle of external walls with two partitions in the middle.
4: After masonry is completed, dry the bricks and then paint them. After the mortar reaches the strength, the peripheral backfill soil is connected to the water injection experiment, and no leakage can occur. Note: Waterproof mortar should be used for painting.
5. The automatic car washing pools on the construction site are all finished products. When the foundation beam concrete reaches the strength (generally 14 days), the "reservoir" in the sedimentation tank is filled with water, and the manufacturer is contacted for installation.
6: It can be put into use after installation and debugging.