Fire record department

Where can I put it on record?

The specific fire control examination and approval items are all at the district and county level. Filing can be operated directly on the website. After confirmation, send the corresponding information to the district-level fire service window.

What is the fire filing process of the Housing and Construction Bureau?

The steps of the fire protection filing of the Housing and Construction Bureau are as follows: The construction unit shall, within seven days from the date of obtaining the construction permit and passing the project completion acceptance, carry out the fire protection design and completion acceptance filing through the fire protection design and completion acceptance filing acceptance system on the website of the fire control institution of the provincial public security organ, or submit a paper filing form, and the fire control institution of the public security organ shall enter it into the fire protection design and completion acceptance filing system for corresponding filing.

Beijing fire online filing inquiry system?

Beijing fire online acceptance and filing inquiry system is the service guide channel of the official website and the window of the capital. You can log in to the service guide of the window of the capital for enquiries.

The window of the capital is the portal website of Beijing municipal government, and all functional departments have business entrances on the website.

Can the fire inspection records be found online?

The record results of fire inspection and acceptance can be found online. For example, the fire inspection project in Changchun can be inquired in official website of Changchun Urban and Rural Construction Committee. Acceptance is divided into two parts: filing and necessary review. Items for the record can be accepted by drawing lots. Unselected items can pass the acceptance record directly without acceptance, and items that must be inspected and tested must be accepted.

600 square meters office fire record process?

first step

1: First, fill in the Application Form for Fire Prevention Audit of Building Interior Decoration Design and the Application Form for Fire Prevention Audit of Building Construction Site;

2. Remember: the reporting unit should be the construction unit, not the construction unit, and the construction unit needs to build the official seal and show the rental agreement or purchase agreement;

3. For example, the fire control procedures are handled by the construction unit, which can only be said to be the agency.

Second step

The contents of the declaration form are basically the main building materials, such as wall materials, floor materials and top materials.

Third step

Copy of the overall fire acceptance drawings, you need to prepare a copy of the overall fire acceptance drawings of the decoration site (generally available in the property management office).

Fourth step

1: Prepare the plan layout, electrical diagram and fire-fighting reconstruction diagram of the specific construction site (if the fire-fighting facilities have not moved, please explain in the remarks);

2. The above drawings need to be printed and stamped by units with design qualification (such as architectural design institute).

Step five

1: The local fire brigade will conduct on-site inspection within 10- 15 working days and submit written opinions.

2: Agreed: We can start work;

3. Disagree: The renovation plan needs to be revised.

Step 6

1: Two weeks before the renovation is completed, you can submit the declaration form for fire control acceptance of construction projects, and the contents are basically the same as the declaration form;

2. Generally, the fire brigade will randomly check 2~3 kinds of building materials for testing, and the testing cost is about RMB 1 1,000 for each kind (PVC pipes, joinery boards, etc.). Most likely to be drawn).

Step 7

If they pass the examination, at least 2 people from the construction unit shall participate in the fire protection training (compulsory).

Step 8

After the project is completed, the fire brigade will go to the site for inspection, and will list the rectification opinions, just follow them, and then send a fire inspection approval letter to the construction unit.

These materials are as follows

1: decoration approval drawing (one set of blueprints) (stamped with special seal for fire approval);

2. Two application forms for fire prevention audit of building interior decoration design (note: online download);

3: Power of Attorney (Party A/Property);

4: Copy of ID card;

5. Design qualification and design basis;

6: Original as-built drawing;

7. Review opinions on the original design of the building (Party A/property);

8. The original acceptance certificate of the building (Party A/property);

9: One application form (Party A/property).